Interconnect Malta has reached a major milestone in the development of Malta’s second electrical interconnector (IC2) with the recommendation for award of a €34.2 million contract for the manufacture and installation of onshore cables.

Following a detailed evaluation process, SELT SpA has been selected to undertake this crucial project phase.

The contract covers the supply, trenching, installation, and restoration of 21 kilometres of high-voltage cable in Sicily, running from the offshore cable landing point in Marina di Ragusa to the 220kV substation in Ragusa.

In Malta, 1.8 kilometers of cable will be laid between the Maghtab terminal and the offshore cable landing site at l-Għallis.

This project is part of Malta’s broader strategy to enhance energy security and increase the integration of renewable energy into the national grid. The IC2 project will double Malta’s electrical connection to Sicily, enabling greater stability and flexibility to incorporate renewable energy sources.

In addition to the onshore cables, two more tenders are currently underway: a €185 million contract for the manufacture and installation of the submarine cable, and a €12 million contract for 220kV switchgear, control panels, and fire suppression systems. Together, these components will form a comprehensive infrastructure to support Malta’s energy future.

Energy Minister Miriam Dalli highlighted the importance of IC2 for Malta’s climate goals, stating, “This project is a crucial step towards our vision of a cleaner, more sustainable energy future. IC2 will provide the capacity needed to integrate more renewable energy, reduce our reliance on traditional sources, and pave the way for future offshore wind and battery storage projects.”

“We are pleased to have recommended for award a significant tender for one of the key phases of the Malta-Sicily interconnection project. This project will effectively double Malta’s electrical interconnection capacity with Sicily, providing substantial benefits to the country. While the complexities and costs involved are considerable, this milestone reflects ICM’s commitment to delivering one of the most critical infrastructure projects in Malta today. We remain focused on ensuring that every step taken is in the best interest of Malta’s future energy needs.” CEO Inġ. Ismail D’Amato said.

Co-financed by the EU under the European Regional Development Funding Programme 2021-2027, the IC2 project represents a significant investment in Malta’s energy infrastructure and long-term sustainability.